156. Fixed duration Tasks and tracking progress over time

193 views
Sep 18, 2023
13:22

If you have a fixed Duration Task Type and want to track the real effort which was spent by resource, you can do it in two ways. One of them is to manually put the real effort, for example, per week, and another is to put the real effort directly to Resource assignment. In this vlog I will explain how to accomplish that and what approach to take