Longest Path vs Critical Path

73 views
May 12, 2026
5:29

Longest Path vs Critical Path Many assume they are the same but they’re not. Critical Path: Activities with zero or less (or defined) total float. Multiple critical paths can exist, each showing potential delays. Longest Path: The single path that drives the project completion date. It reflects the overall project delay and forecasted finish. In Primavera, filters distinguish both: “Critical” by float definition, and “Longest Path” by completion driver. Understanding this difference is essential for accurate schedule analysis and delay assessment. Check our project control courses https://smartpmtraining.com/courses/ Check our construction digital transformation and AI solutions https://www.novycore.ai