Construction at the Santos GLNG plant on Curtis Island has reached another key milestone, with the delivery of the final two modules for the LNG processing units.
These massive structures , while not the heaviest, – known as modules – have a combined weight of more than 2,890 tonnes and are the last of 111 modules required to finish building the two LNG processing two units – known as trains – that will convert natural gas into liquid.
Bechtel is constructing Santos GLNG’s two-train LNG plant on Curtis Island, off the coast of Gladstone.