Task Type in ms Project - Fixed Unit, Fixed Work, Fixed Duration. Microsoft project task types.
When you assign a resource to a task in Microsoft Project 2019, there is a well-defined mathematical relationship between three fields: Work, Duration, and Units. Microsoft Project uses the following formula to calculate the values of these fields: Duration= Work/Units
Task Type in Microsoft project
======================================================
Checkout PowerApps Real Time Projects
https://tipsbyanil.com/power-apps-real-time-projects/
=======================================================
Work- Total amount of work to complete a task e.g. Complete assignment
Duration- Time to complete the task e.g. 2hrs
Units- The percentage of resource time on a task e.g. 50%
Task Type in Microsoft project
For example, if a resource is assigned 40 hours of work at 100%units, the duration of the task will be 40 hours or 5 days. If the resource is working only 50% of their time on this task, then the duration is 80 hours or 10 days.
Task Types and Scheduling in ms Project
Fixed Duration, Fixed Work, Fixed Units
Duration= Work/(Fixed)Units
In these 3 values if one is constant then the other 2 values will be auto calculated by MS Project
Task Type MS Project Auto Calculation
If one of the three values (work, duration, or units) is fixed, and you change a second value, the third will be re-calculated and changed by Microsoft Project.
1. Fixed(U) - Change(D), Auto(W)
2. Fixed(D) - Change(W), Auto(U)
3. Fixed(W) - Change(),U), Auto(D)